Civil Works of the converter station for EstLink2 project
Client: Siemens Osakeyhtiö Estonian Branch
Construction period: January 2012- August 2012
Construction cost: 3 295 000 EUR excl. VAT
According to the agreement, following works will be executed:
-General construction works of convertor station
-Foundation, building works, site works etc.
-Transfer station with the capacity of 650MW