Railway reconstruction
Client: EVR Infra AS
Construction period: 19.10.2009-31.05.2010
Construction cost:: 5 500 000 EEK (351 000 EUR) excl. VAT
According to the agreement, following works will be executed:
Road repair by means of installing reinforced concrete crossties – 16 000 m
Dismantling of roads and improving roads geometry by means of a ballast tamping machine – 1 000 m
Replacement of wooden crossties – 4 450 pcs