Design and construction works of Tallinn Old City Harbour new pedestrian bridge
Client: AS Tallinna Sadam
Contract period: april 2020 – july 2021
Construction cost: 4 222 222,22 EUR without VAT
According to the agreement, following works will be executed:
All the needed design and construction works delivering new movable bridge according to the contract.
Technical data:
- Length – 44 m
- Total weight of the steel structure – 130 t
- Moving part – Bridge turns around the vertical axis
- Depth of the foundation – – 37m below sea level
- Mechanical part – electrical drive system with slewing ring