The total cost is 2 980 565,71 EUR excl. VAT.
The deadline is December 2012.
The contract includes the design and construction of biogas plant CHP which is used to produce electricity and warmth.
The plant includes 2 primary fermenter with diameter of 23m, height of 6,4m and 1 post-fermenter with diameter of 30m, height 6,4m, technical building, slurry receiving and dosing unit, solid matter charging system of maure and other technological equipment and constructions. It also includes CHP units offered 1200kWel. The power supply is from Eesti Energia distribution network for 15kV.
The project manager from KMG Inseneriehituse As:
Hr. Marko Pikk
Tel: +372 55 59 69 24
E-post: marko.pikk@kmg.ee